Tuesday 6th April 2021 to Saturday 15th May 2021
**********************************************************
Tuesday 6th April 2021
Wednesday 7th April 2021
"Bathroom / Ensuite Floor and Wall Tiles"
"Kitchen Counter Tops"
Note from Geoff to Brett
8.55am now ... just back from "My Walk"
One guy on site ... Tiler
He is working on the Bathroom Walls in Unit Three
I'll go back early afternoon and see how he's going
And maybe get a photo or two !!
Workout tonight ... we'll call in again on the way home
Enjoy Your Tuesday !!
Brett
Thanks
Geoff
It is now Twelve Midday
One Photo below showing the Wall Tiling Work in the Unit Three Bathroom Area
( two tilers on the job now )
There are also a couple of guys there from Pacific Kitchens
They are working on the Kitchen Island Cupboards in Units Two and Three
Will go back later or we might leave it until after the Workout
Have a look around then... plus do the keys and lockup as we told Ash, etc, etc
Brett
Okay ... Cool !!
Progress slowly but surely
Sharon
It is 5.50pm Tuesday now
We've just been to '#32' with Michelle
The Kitchen Counter Tops in Units Two and Three are finished
And they look terrific !!
Michelle reckons Unit Four will be done tomorrow
Dad took a "before" photo and he will send this and the "after" shot to you tomorrow
Geoff and it's 9.30am on Wednesday now
Just back from Anderson Street
There are Three Tilers on the job
I know absolutely nothing about Tiling
BUT ... this work seems to be going at an Extremely Slow Pace !!
That is just my opinion
I didn't want to disturb them but I did manage to get a shot of the Unit Four Ensuite Shower Area
which now has a few Floor Tiles and this photo is below
The Kitchen Guys have not turned up yet ... Bugger !!
As Sharon wrote / text yesterday, I have a "before" shot of the Unit Four Counter Tops
Although you are not getting that until I can also send an "after" shot !!
Will go back later in the day ... give the guys time to do 'stuff' !!
Have a Good Day and there are Curried Sausages made by your Mummy in the freezer if you want them !!
Brett
I’m okay for food !! ... but Thanks
Well, by the time you send it I may have visited the site !!
Geoff
I will still send it !!
Brett
Okay
Geoff
Well, it is 2.45pm on Wednesday
And there are Three Videos attached
Number 01 - Thirty Six Seconds
I think the guys must have read my note to you about "slow" !!
Because the First Part of this video shows that the Ensuite Floor is just about finished !!
And the Second Part is about the Bathroom Walls also being nearly finished !!
Number 02 - Fourty One Seconds
The Kitchen Guys have been and gone
And here are the Counter Tops in Unit Four !!
And as your Mum said, they do look Terrific !!
PS - the "before" photo is just below as well
Number 03 - Nineteen Seconds
As I was leaving, this truck turned up and dumped a heap of soil
Sharon
It’s all just too much !!
I Love, Love, Love It !!
Brett
Looking Great !!
The Counter Top looks great with that overhang for seats
Three new seats coming !!
Sharon
Mum here ... yep !!
Geoff
The "High Seats" will come as soon as we move in !!
Thursday 8th April 2021
Friday 9th April 2021
"Bathroom / Ensuite Floor and Wall Tiles"
"Paths and Landscaping"
"Kitchen Counter Tops"
Note from Geoff to Sharon and Brett
Attention -- Sharon Margaret Coudrey
Three Photos Below
Brett has seen these in 'real life' ... so this note is mainly for YOU !!
Look at the Pretty Little Tiles that are being put up in the Unit Four Bathroom Area !!
And the same type of thing is going to be done in the Ensuite
( as I understand it, all the Units will have this sort of feature )
More Things Being Done To Make You Happy !!
BRETT ... the Two Fence Payments went through perfectly
I have Official Receipts to give you the next time you are out here
Brett
Thanks
And it is 5.45pm on Thursday
There are Two Videos attached
Number 01 - Fifty Seconds
Number 02 - Thirty Seven Seconds
Both show that organising the Paths and Landscaping out the front of the Units is underway !!
There will be definately more of this tomorrow !!
We did not go in any of the Units ... too dark inside
Will go back in the sunshine tomorrow !!
Reminder ... It's Sharon's "RDO Friday"
Brett
Looking Good !!
Geoff
Exciting Times !!
Hi, Brett ... and it is Friday at 10.00am
Your Mum and I are just back from "That Bloody Place" !!
There are Four Videos below
Number 01 - Fourty Nine Seconds
And here is Mr Ash Moseley doing the Boxing and Levels on the Paths
He can't stay all day but is going to do as much as he can
Number 02 - Fifty Two Seconds
The Kitchen Counter Tops are Finished completely !!
This video shows the "Brett's Breakfast Area" and the end has also been added
Plus ... the Sinks are in !!
And, of course, the video finishes with a "zoom-in" on "Coudrey Hill"
Number 03 - Fifty Four Seconds
The Bathroom Area in Unit Four is done !!
Floor and Wall Tiles and just the Grouting to do !!
Number 04 - Twenty Eight Seconds
Look at the Ensuite !!
A Whole Wall of the "Little Tiles" !!
Your Mother Loves Every Bit Of 'Brett's Unit Complex' !!
We told Ash about the "broken lock" on the Unit Four Rear Door
He is going to have a look at it and if necessary, get it replaced
Will let you know what happens
Brett
Looking Terrific !!
And below are a few Photos taken by Your Mum !!
Saturday 10th April 2021
"Trinity Beach -- Walk / Trek"
"Powerboard"
"Michelle and Ash Moseley"
"Paths and Landscaping"
Note from Geoff to Brett
One Video Right Here - Fifty Seven Seconds
My emphysema seems to be getting a bit better
So your Mum and I decided to do this "Walk - Trek"
It is new to Trinity Beach and is Very Challenging
Pushing your way through because it is overgrown
But we guess it will be tidied up one day
And it will become a Pleasant Little Walk !!
The Powerboard has now been installed / connected
It is in Bedroom #2 ( and this will become known as a Storeroom )
There are Two Photos included below
Note from Geoff to Ash Moseley Homes
And here are Michelle and Ash working on the Levels for the Paths
There is a Fifty Three Seconds Video Here along with Seven Photos below
Michelle working with Hat On and Hat Off
Oh, yeh ... you can also see the "HALO -- Supervisor / Boss" in these shots
Michelle
Great photos and videos !!
All in a days work !!
Geoff
Thanks, Michelle, for your note about the above Video and Photos
Plus the attached photo
Will you please tell Ash that both He and I are "Honest and Trustworthy" !!
Michelle
Will do !!
Tuesday 13th April 2021
Wednesday 14th April 2021
"Ensuite Bathroom in Unit Four"
"Driveway"
"A Walk Along a Garden Path"
"Concrete Reinforcing"
"Kitchen Splash-Back Tiles"
"Front Fence"
Note from Geoff to Brett
And I got back from "#32" at 8.15am
Ash was there but he left as I walked in
Only One Car and One Guy on site ... and he is Tiling
( with the amount of tiling to do, you'd reckon there'd be twenty guys there !! )
He is working in Unit Two
There are no changes to anything where Your Mother is going to live !!
There is One Fifty Six Seconds Video Right Here
I like the "look" of the Unit Four Ensuite, so I did another "walk through" !!
There are also Two Photos below
It seems like things might happen soon with the New Driveway
Because the Old One is marked 'REMOVE' !!
Will go back again mid-afternoon and after tonight's Workout
Sharon
Ensuite Bathroom does look nice !!
And it is now 2.00pm Tuesday
Still just One Car / One Guy / One Tiler on site
No changes anywhere ... except the Bathroom in Unit Two
And here is a Fifty Seven Seconds Video
And it is titled ... "A Walk Along A Garden Path"
I will do an Updated Version when the concrete is laid !!
Mum here and the time is 5.50pm
No changes anywhere
Everything is locked up tight
We will see what happens tomorrow
Goodnight
Brett
That is all okay ... Thanks
It is Wednesday at 10.25am now
Going for "A Walk" now
"New York City" cap is on the head !!
Will write again soon
Brett
No worries
Hope there’s some progress !!
Wednesday at 11.10am ... Back From "The Walk"
There are Two Videos attached
Number 01 - Fourty Four Seconds
Look at all the work vehicles on site !!
And the video starts with the dug-up old driveway
Then it shows what I reckon is the Roof Lining for the Carports that Michelle mentioned a while ago
I guess we will soon see if I am right or wrong
And, as you can see, an excavator is on the job
Number 02 - Fourty Five Secondx
Here you can see that the Boxing-Out for the Driveway has started
The guys are having smoko in the carport and two of these are Ash and Ethan ... said hello, etc
And I went inside to look around ... Three Tilers on the job !!
In Unit Four, the Bathroom and Ensuite Tiling is all Finished ... except for the Grouting !!
There was one guy working in the Kitchen and he reckons he'll have the 'Splash-Back Tiles' done today
And, yep, we will go back later
And finally there is a Photo of Me !!
"I Love New York City"
Brett
The place is Looking Great !!
And You Too !!
Geoff
ONLY because the camera is in front of my face !!
Geoff at 2.37pm Wednesday
More videos coming in about Thirty Minutes !!
And there are Three More Videos attached
Number 01 - Eighteen Seconds
Ash and others digging out the footings / foundation for the Front Fence
Digging by Bloody Hand !! ... in this Heat !!
Number 02 - Fifty One Seconds
Rio being laid all along the paths
Number 03 - Fourty Three Seconds
Kitchen Splash-Back Tiles
The guy did not have time to finish them today
But he promises tomorrow !!
And this video shows that a lot are lying on the counter tops and ready to go
And, of course, there is "The Hill" !!
Two letters for you ... from your neighbour who was holding them
Both are from O'Brien Real Estate of Clifton Beach
One is addressed to you at Unit One and the other at Unit Two
( the old days, eh !! )
Sharon at 4.45pm Wednesday
It’s been raining steadily here at Trinity Beach
Drove past Your Place and Tanya’s Plaque but didn’t get out of the car
Have a nice night
Brett
Everything Is Looking Pretty Good !!
Thought there might have been Tiles on the Kitchen Walls
Sharon
As Dad wrote above, the guy said tomorrow !!
Thursday 15th April 2021
Friday 16th April 2021
"Front Fence Foundations"
"Rear Area of the Unit Complex"
"Four Storage Sheds"
"Council Bin Area"
"Grouting in the Unit Four Bathroom"
Note from Geoff to Brett
9.30am and I am just back from "The Marathon"
LOTS - BLOODY - HAPPENING !!
Will be sending you Photos and Videos in about thirty minutes
And here are Three Videos !!
Number 01 - Fourty Four Seconds
The Front Fence Foundations have been poured !!
Such A Surprise !! ... they were only dug-out yesterday !!
Number 02 - Fourty Seconds
Cleaning up The Rear of the Unit Complex !!
WOW !!
Scroll up for a look at the "before" video on Saturday 10th April !!
Number 03 - Thirty Two Seconds - taken later in the day
Levelling The Area !!
There are Two Photos below
Yesterday I mentioned that I "guessed" this was the Carport Roof Lining Material
Today Ash told me it is the Walls for the Four Storage Sheds
The Carports will be lined with the same material used on the Eaves
And it is just on 8.00am Friday
There is One Fifty Five Seconds Video Here
It starts with the "Ready To Pour Council Bin Area" and then there is A Walk Along The Back Of The Units
( the 'porta-potti' is a very important part of any building site !! )
Only the Three Tilers were on the site
I spoke to them and they have had a change of plans
All the Bathrooms are going to be finished, including the Grouting, before any Splash-Back Tiles are done
It doesn't really matter ... one day they will be there !!
Going to go back just after lunchtime
Brett
That’s okay
They’re still going on with it !!
Right on Midday Friday now
Still just the Tilers on-site
There is a Fourty Six Seconds Video Here
And this shows that the Grouting in the Unit Four Bathroom has been started
The Ensuite is still waiting it's turn !!
Your Mum works until 5.00pm on Fridays
We will see what the light is like when she gets home
Plus check all the Locks, etc, etc
Maybe see you for "FOOD" tomorrow morning !!
Brett
Looking Great !!
2.55pm now and just got back from "#32"
As I arrived there, the Tilers were just leaving
Hopefully, it might be "A Big Working Saturday" !!
We shall see, eh !!
Have a Good and Enjoyable Night !!
Brett
I doubt there will be anyone there tomorrow
But you never know !!
Sharon at 5.45pm Friday
No changes and everything is locked up tight
See you tomorrow
Saturday 17th April 2021
"Kitchen Splash-Back Tiles"
Note from Geoff to Brett
7.15am and I've just been for "A Little Drive"
Unit Four ... Kitchen Splash-Back Tiles have been started !!
Three Photos below and these were taken via 'flash'
Will take some 'daylight' ones later
And here are Two More Shots taken without the 'flash'
The Colour Name of the Tiles is "White Crystal"
PS - I think the ones above are better !! ... truer colour !!
Monday 19th April 2021
Tuesday 20th April 2021
"Rain + Rain + Rain"
"Rain in Trinity Beach"
"Ground / Garden Drains"
"Unit Four -- Door Frames and Doors"
"Laundry Tub"
"Door to Geoff's Office"
"Vanity in the Ensuite Bathroom"
Note from Geoff to Brett
Brett
You have to much time on your hands !!
From Geoff a little bit later in the morning
This "Water Stuff" Is Ridiculous !!
Our backyard is flooded and all the drains are full
Feel 'really pissed' for you
Because we know that you just want the place finished !!
And get the Paying Tenants in !!
Maybe the Tilers turned up
But there is not a hope in hell of walking over without getting soaked
Brett
Don't even worry
It's supposed to rain all week
There won't be any concrete getting poured tomorrow, I don't think !!
Brett
Five cars there today as I drove past
They must be doing internal stuff ... skirting, frames, etc
Sharon
Ha Ha !!
Dad can’t go 'cause he won’t take an umbrella !!
Brett
You’ll have to take him for a "mud walk" tonight then !!
Geoff
The rain hasn't stopped even for a second !! ... no walking !!
Hope for "SUNSHINE" tomorrow !! ... but not very likely, eh !!
Sharon later in the Evening
Mum here ... Shitty Weather, eh !!
Brett
Yep !!
Geoff on Tuesday 20th April at 6.00am
Light rain here so I am not going over with Sharon at 6.30am
Have got a jacket and bag ready and I'll go for a walk as soon as there is a break
As well as the concrete pour, I want to see if anything went on in Unit Four yesterday
Will get back to you as soon as possible ... whenever that might be !!
Brett
No rush
I don’t expect anything today
Geoff
6.40am ... and it is Absolutely Pouring Down !!
Note from Geoff to Ash and Michelle Moseley
Don't worry about tomorrow !!
These People and their Umbrellas are going to be there at 7.00am to protect the new pour !!
Michelle
Pretty sure we won’t be pouring concrete tomorrow with this weather
Geoff
I sorta guessed that !!
Bloody Rain !! ... has not stopped even for a second !!
Would you mind letting me know any updates, days, times, etc
Thanks
Michelle
Certainly ... Will Do !!
Geoff on Tuesday 20th April at 6.45am
And I'm guessing that all your Concreters are still home and warm and dry in bed
Because it is pouring in Trinity !!
Michelle
Yep !!
From -- The Cairns Post ... Monday 19th April 2021 and Tuesday 20th April 2021
More than 200mm of rain falls across parts of FNQ as school term starts
Parts of the Far North have recorded more than 115mm of rain in five hours Monday
as Bureau of Meteorology issues an initial minor flood warning and warns of more heavy rainfall
More heavy rain is forecast for the Far North in coming days,
with the Bureau of Meteorology issuing an intial flood warning on Monday
A nearby trough dumped up to 260mm of rain over the region in the 24 hours from 9am Sunday to 9am Monday
and conditions haven’t let up
While the big totals were initially recorded to Cairns’ south on Sunday,
the rainfall has shifted north with Whyanbeel Creek, north of Mossman, collecting 116mm in 5.3 hours on Monday
Closer to Cairns and in the same period, Saddle Mountain recorded 85mm, while Cairns Airport had 61mm
In its flood warning for the Mulgrave and Russell rivers,
the Bureau warned minor flooding may develop at Peets Bridge and Gordonvale from midafternoon Monday
“Widespread rainfall totals of 150-240mm
have been recorded since 9am Sunday in the Mulgrave and Russell River catchments” the BOM said
“Further heavy rainfall is likely during the next few days”
Bureau forecaster Rosa Hoff said the Far North could expect rainfall equivalent
to what we had yesterday and today, if not potentially heavier
“At this stage we are expecting (Tuesday) to have the last really significant chance of heavy rainfall” she said
“We could potentially see heavier rainfall extending through to Thursday,
with potential for further falls beyond that, whether they’re heavy or not”
The BOM’s current forecast is predicting anywhere from 80 to 120mm
over Cairns and 90 to 150mm over Innisfail on Tuesday
A tropical low has also been driving heavy rainfall in the Cape and Torres Strait,
Bureau forecaster Kimba Wong said
Horn Island recorded 143mm in the 24 hours to 9am today
“The chance of developing into a cyclone is not looking likely at less than five per cent,
but it may enhance wet weather across the region as it tracks toward the Gulf of Carpentaria” she said
“From there, what happens will depend on how deep the structure of the low gets
If it remains shallow it may waffle around the Gulf,
but if it becomes deeper it could interact with another trough”
Ms Wong said the Bureau was looking at putting out a flood watch
for Far North river catchments on Monday afternoon
“Given the rainfall we’ve had and what may still be to come,
we’re looking at the potential for a flood watch” she said
“The saving grace is there hasn’t been too much rainfall in the weeks leading up to now,
so the catchments aren’t particularly saturated
If it’s issued, it will most likely be for the Tully, Murray and Daintree River catchments”
Cairns Racecourse had nearly 190mm of rain in the 24 hours to 9am today,
while Cairns Airport recorded 159mm in the same period
The heaviest falls have been south of Cairns,
where Babinda boosted its 2021 Golden Gumboot prospects with 259mm at the Boulders
Saltwater Creek at Innisfail had 239mm and the Innisfail Airport 223mm
The wet weather has contributed to traffic chaos across the region,
with the Bruce Highway shut earlier due to a crash and vegetation and flooding impacting roads
Earlier -- It could be a wet return from school holidays for Far North students on Monday
with parts of the region in line for late wet season downpours of up to 100mm this week
A trough sitting off the coast is set to make its move, with Tuesday expected to see the biggest falls,
according to Bureau of Meteorology duty forecaster, Shane Kennedy
He said areas around Innisfail, Cardwell and Port Douglas would probably be the wettest,
although Cairns could potentially receive up to 25mm on Monday, increasing to 50mm on Tuesday
“It’s all being caused by a trough in the Coral Sea and that is moving closer to the coast” he said
“We might see a bit making its way onto the Tablelands as well”
Storms are also forecast to impact the region on Tuesday
Conditions are expected to begin easing on Wednesday and further improving later in the week
Mr Kennedy said daytime temperatures would likely hit about 29C, while remaining around average overnight
Note from Geoff to The Wife and The Son
Our Backyard at 8.00am Today
Eighteen Seconds Video Here
The rain has not stopped even for a moment !!
And I bloody well want to go for "My Daily Walk" !!
Brett
Hasn’t stopped here either !!
Geoff
It is almost 9.30am Tuesday
The rain stopped and I am back from "My Walk" !!
YES - YES - YES ... I got Photos and Videos !!
Please give me thirty / fourty minutes to get them organised and uploaded
Brett
Okay
Geoff
9.55am ... glad I went when I did ... because it is pouring rain again !!
And I am still working on the Photos and Videos !!
Geoff
There are Three Videos attached
Plus Four Photos are included below
Video 01 - Fifty Six Seconds
This shows that the new drains are working perfectly !!
Look at the water pouring through !! ... Bloody Terrific !!
Video 02 - Eighteen Seconds
The Door Frames and Doors are going into Unit Four
( and Ethan is 'The Man' )
And the "Fancy Finish" on the Doors is on both the Front and the Back
Video 03 - Fourteen Seconds
The Laundry Tub has been installed
Photo 01 - The Laundry Tub
Photo 02 - The Door to Geoff's Office
Photo 03 - Vanity in the Ensuite A
Photo 04 - Vanity in the Ensuite B
10.30am Tuesday now ... still pouring rain here !!
Brett
Thanks for going over
And it is Looking Good !!
Really glad the drains are working properly too
Keep the place 'semi-not-flooded'
Bathroom Cabinet looks great as well
And the Grouting that has been done
All Very Nice !!
Sharon
The Ensuite Bathroom is gorgeous !!
And everything else is great too !!
Thursday 22nd April 2021
Friday 23rd April 2021
"Ground / Garden Drains"
"Unit Four ... Main Bedroom"
"Unit Four ... Geoff's Office"
"Garden / Access Paths"
Note from Geoff to Sharon and Brett
It is 9.50am and "Hello" to my Wife and Son
Have just been for "The Compulsory Daily Walk"
Have a few Photos and Videos
Just give me a little time to organize and upload them
Brett
You’ve got til 10:40am because I have to head out !!
Hurry !!
Geoff
I will try !!
Sharon
Ha Ha !! ... Under Pressure !!
Geoff
There are Four Videos attached
And One Photo coming soon !!
Number 01 - Fourty One Seconds
Water coming into the property
But the New Drainage System takes it out to the gutter / street !!
Number 02 - Fifty Seven Seconds
A look around Sharon and Her Husband's "Love Nest"
Fancy Doors and Skirting Boards !!
Number 03 - Fourty Five Seconds
A look around Geoff's Office
Fancy Doors and Skirting Boards !!
Number 04 - Thirty Five Seconds
The Kitchen Splash-Back Tiles are Finished !! ... except for the Grouting !!
Brett
Looking Pretty Good !!
And I am real glad the Drains Work !!
Sharon
I like My Shiny Tiles !!
Geoff
Below is the photo I mentioned in my earlier note
I was going to ask why is there Two Rows of Foundations at this end of the Fence
BUT
I was sensible !! ... and looked at the Fence Plan you sent us a while ago !!
And answered my own question !!
There is going to be a Garden Bed between these Rows !!
Reckon this will look real good from the street, eh ??
I will leave you both alone now
Note from Sharon to Brett
11.15am Friday now
Guys on site doing door frames, tiles, grouting, etc
And below is One Photo
Dad and I were sitting on the Carport Floor so here is a Ground Level Shot !!
"The Paths"
They could not be poured last Tuesday because of the heavy non-stop rain
Now hoping for Tuesday 27th April 2021 !!
Saturday 24th April 2021
Tuesday 27th April 2021
Wednesday 28th April 2021
"Vanity in the Unit Four Bathroom"
"Concrete Pouring of the Paths"
"Ash and Michelle Moseley"
Note from Geoff to Brett
It looks Really Terrific !!
There is a Video RIGHT HERE - Thirty Four Seconds
Along with Two Photos below
Tuesday 27th April 2021
Note from Geoff to Brett
Good Morning
7.40am ... and I'm back from "The Compulsory Walk" !!
Guess What ?? ... there is no concrete being poured !!
Maybe it will be Thursday now ... hope Michelle lets me know as she said she would
BUT - there are five cars there and guys going in and out of all the Units
Skirting boards, door fames, bits of tiling and grouting, etc, etc
Will check again later ... and Sharon has a 4.00pm knock-off today
Brett
Yep ... okay
It is now 1.45pm Tuesday ... just back from "#32"
There has been Two+ Hours of Bloody Terrific Hot Sunshine
And I was hoping for "Any Sort Of Outside Work" being done !!
But 'NO' !!
All the workers' cars are all still there and lots of noise from each of the Units !!
Hope this weather holds and "Things Start To Happen" !!
Brett
There is no outside work going to happen !!
Need more than two hours of sunshine !!
Geoff
Just Hoping !!
It is now 7.50am Wednesday
Just back from "My First Walk Of The Day"
Two cars on site and the guys are working in Units One and Two
Three and Four were both locked up and I didn't bother anyone for the key
Pretty sure that nothing would have changed very much anyway
Will check again later
!! !! -- the concrete has NOT been poured -- !! !! -- just letting you know !! !!
Brett
They are going to try and pour tomorrow
Geoff
FAN--BLOODY--TASTIC !!
I will be there at 6.30am !!
Brett
I will try too
Geoff
See You There !!
Note from Geoff to Ash and Michelle Moseley
I heard a rumour that the "below" could happen tomorrow morning !!
Michelle
Fingers crossed !!
It is now 1.30pm Wednesday ... Back from "The Walk"
There is One Video RIGHT HERE - Fifty Seven Seconds
It is a Final 'BEFORE' Look at the Paths and Other Areas
Going to be Very Damn Different at this time tomorrow !!
Unit Three is now open as well but Four is still locked up tight
Might get in there tomorrow to have a look around
Brett
Yep !!
And you can ask Tanya for no rain tonight
Geoff
Praying Hard to Her and God !!
Brett
God !!
Jeez ... are you okay !!
Geoff
He also has something to do with the Weather !!
Thursday 29th April 2021
Friday 30th April 2021
Saturday 1st May 2021
"Concrete Pouring of the Paths"
"Rain + Rain + Rain"
"But The Job Got Done"
Note from Sharon to Brett
4.00am Thursday
Fucken Steady Hard Rain At Trinity Beach !!
What the hell do we do ??
PS -- Dad told me to write the "F" word !!
Geoff
4.50am ... just a light drizzle now
Spoke to Your Sister and told her to take the wet stuff away !!
Geoff
5.20am ... STOPPED !!
Brett
I hope it stays away !!
Geoff
TANYA MARY RONEBERG
Please stop this and let the "Paths Be Poured" !!
Brett
It’s pouring in the city
Geoff
Same Here !!
We are going to park outside "#32" for a while and see what happens
Note from Ash and Michelle Moseley
Pour has been put back to 7.30am because of the rain
Hopefully it clears
Sharon
Thanks for this note
Please let us know if there are any further changes
Fingers Crossed !!
Brett
7.59am Thursday ... THEY - ARE - POURING - RIGHT - NOW !!
Geoff
9.45am now and I just got home
Really liked watching all that Activity and Machinery !!
Pump Truck has gone and the Concreters are having 'smoko'
I am going to go back later
PS - the weather has fined up a lot !! ... even sunshine at times !!
Brett
No worries
Good to see and hear there's progress !!
Geoff
Just downloaded Thirteen Videos from the camera !!
Going to take me a while to sort it all out !!
These are listed here in the order they were taken
That is, as the day and the pour progressed
Number 01 - Fifty Six Seconds
Number 02 - Fourty Seven Seconds
Number 03 - Fourty Three Seconds
Number 04 - Fourty Three Seconds
Number 05 - Fourty Three Seconds
Number 06 - Fourty Six Seconds
Number 07 - Fifty Six Seconds
Number 08 - Thirty Three Seconds
Number 09 - Fifty Six Seconds
Number 10 - Fourty One Seconds
Number 11 - Fourty Six Seconds
Number 12 - Fifty Five Seconds
Number 13 - Fifty Three Seconds
Geoff ... and it's 10.30am now
Going back to "#32" to take a few more !!
PS - Hang On !! ... it just started to rain hard !! ... waiting !!
Geoff
Another "Little Walk" and I got back here right on Midday
Guys are still there working
Good Thing ... All The Black Plastic Cover Has Been Removed !!
And It Looks Terrific !!
Two Videos are attached
Number 01 - Fifty Seven Seconds ... taken from Unit One end
Number 02 - Fifty Four Seconds ... taken from Unit Four end
Sharon
Looks Fantastic !!
We will be "skipping" down there soon !!
Brett
Looking Good !!
Geoff on Friday 30th April 2021
It is just coming up to eight o'clock now
Going for a walk soon to see "The Finished Result"
Will send the Photos / Videos to you as soon as I can
Geoff and it's Friday now at 8.30am
There is One Video Here and Two Photos below
PATHS --- --- THE - FINISHED - RESULT !!
The video runs for Fifty Seven Seconds
And the two photos show the Exposed Aggregate Finish
It looks Absolutely Fantastic !!
Ethan plus one guy were there working
No-one else was on-site
Brett
Looking Great !!
Note to Ash and Michelle Moseley
The "Exposed Finish" on the Paths is "Simply Bloody Fantastic" !!
Michelle
Agreed !!
Geoff on Saturday 1st May 2021
There is One Video Here - Fifty Five Seconds
'Breakthrough Joe' cutting the Expansion Joints in the Paths
And he's assisted by Brettt ... who got covered in Concrete Dust !!
Thursday 6th May 2021
"The Old Duplex"
Note from Brett
Just looking at Google Earth for some work stuff
And looked at the block !!
The old duplex is still there and it looks so so different now !!
Geoff
Three Photos Below
I downloaded these from Google Earth on 5th April 2020 ... HERE
Yes, your 'word' is one-hundred-percent correct !!
""DIFFERENT"" !!
Brett
You dont need to send me the pictures, Dad
I was just looking at it
Brett
You probably never noticed this but look at how many trees next door has cut down
Geoff
Yep, I saw that !! ... looks like dozens !!
Tuesday 4th May 2021
Wednesday 5th May 2021
Thursday 6th May 2021
"Painting ... Preparation Work"
"Carport Ceilings"
Note from Geoff to Brett
Tuesday and it's 8.45am
Just back from "My First Walk Of The Week"
As the video shows, there is just one car there at the moment
He is one of the Painters and is doing 'Preparation Work'
He said that "there will be a few other fellows there tomorrow"
Reckons they will be finished in "a week or so"
They are Spraying and not Brushing which surprised me !!
The Video Here runs for Fourty Eight Seconds
It is a "BEFORE LOOK" at the front of the Unit Complex
I will do an "AFTER" when it's all finished !!
HAVEAGOODWEEK
Brett
I hope they get shit done !!
I hate seeing Only One Car there !!
Geoff
SO - DO - I !!
11.15am now and it's raining a bit
If it stops I will go for a walk later on and see who may have turned up
Sharon has 4.00pm knock-off and it's a Workout Night
Brett
I was just there picking up the saws but there’s still only one truck there
Geoff
F**K !!
Geoff
It's 2.00pm now and just back from '#32'
Same Car -- Same Position !!
Hopefully tomorrow "The Carpark Will Be Full" !!
Brett
What was he doing ??
Covering things in plastic ??
Geoff
Little, little fillings and gaps in the walls and door / cupboard frames
I watched him for a while ... very quick and efficient !!
Wednesday 5th May 2021 ... note from Brett
Hope there’s cars everywhere !!
Geoff
I am going over in about Fifteen Minutes ... will let you know !!
Brett
Okay
Geoff
It's now just on 9.00am
Three cars there and they all look to be Painters
Still doing Filling and Sanding and Prepartion Work
One of the guys told me that they hope to be Spraying on Friday
Something happened though !!
The Paint Was Delivered - as you can see in the photo below !!
Beautiful Day out here ... and I'll go for another look later
PS - I cannot remember if I have taken a shot of the Laundry Cabinet and Trough
So one of those is also below
It is now 2.15pm on Wednesday
Still just the three cars / Painters on site
There is One Video Here - Thirty Two Seconds
They are currently getting rid of all the black plastic on the front patios
And laying and fixing brand new stuff
Can't have the fancy timber look tiles mucked up with the painting, eh !!
They were really busy so I did not bother them
No 'Protection Plastic" has been fixed anywhere inside as yet
Sharon knocks off at 5.00pm tonight
If it's good light, we will go for another look
Or else tomorrow morning
Brett
Thanks !!
No rush
Hopefully they paint tomorrow
Sharon
5.45pm and we are at your place
All the front patios have been covered but nothing inside as yet
Dad reckons the painting will start on Friday like he was told
Brett
No worries
Thursday Morning at 9.00am
There are Two Videos attached
Number 01 - Sixteen Seconds
This guy is "cutting back the concrete"
And I do not have a clue as to why !!
He said he is only doing the strip which will be the base for the Storage Sheds
Maybe it also means that these sheds are going to be started soon, eh !!
Number 02 - Fourty Nine Seconds
You can see the Sprayer / Compressor at the start
And all the doors from the units have been taken down and are now standing on the front patios
Units One to Three are done and Unit Four will be later today
The guy reckons that's how they do it for the number of coats, etc
All this stuff happening that I don't really understand !!
The masking has started inside with the bathroom floors all covered up
Kitchens will be later
Things are rocking !! ... and The Painting Is Tomorrow" !!
Brett
Okay ... that’s good !!
Remember the concrete is being ground because the rain came before they had finished
Ash wants a nice surface
I might pop out later or tomorrow
And it is now 1.45pm Thursday
LOTS - BLOODY - HAPPENING !!
Seven cars are on site !!
Two Videos are attached
Number 01 - Fourty Nine Seconds
Ethan and his mates putting up the battens in the Carports
Number 02 - Fifty Four Seconds
Masking and more Masking and more Masking !!
Every Where In Every Unit
Looking forward to "The Painting" tomorrow
Brett
You're giving me a headache with all that moving !!
Geoff
Ha Ha Ha !!
Friday 7th May 2021
Saturday 8th May 2021
Monday 10th May 2021
Tuesday 11th May 2021
"Front Fence"
"Carport Ceilings"
"Storage Sheds"
"Painting"
Note from Geoff to Brett
Friday Morning
Guess What ?? ... there are Ten Cars at your place !! ... and lots of guys !!
There is a Fourty Six Seconds Video RIGHT HERE ... and this shows ---
..... the blocks for the Front Fence have been delivered
..... all the battens in both Carport Ceilings are finished
..... they have started building the Storage Sheds
Painting has started and the first Two Photos below show the "outfit" the guys are wearing
Doing all the doors on the front patios first ... nothing inside has been done
The last shot shows the Doors from Unit Four
Action !! ... Lots Of Action !!
Brett
Not Bad !! ... shits getting done !!
Geoff
Yep and Yep Again !!
Your Mum and I are going back for another look between 3.30pm / 4.00pm
Will let you know the changes, etc, etc
Brett
Okay ... and Thanks
Friday at 4.30pm
There are Three Photos below
The first one shows that the framework and insulation on the Storage Sheds is almost finished
Maybe the cladding will be done tomorrow ... maybe !!
The next Two Shots show the Paintwork in Unit Four
It could be the final coat or there could be more to come
We will see what happens tomorrow or next week
Brett
Looks Great !!
Saturday now at 7.00am
Your Mum is being lazy and lying in bed !!
I just went for a drive
Two cars are there, and it looks like more "Carport Work"
Did not stop and go in ... will do that later
From Sharon at 4.30pm on Saturday
Just been to your place and no big changes
Ric and Annike turned up and we showed them through all Four Units
They loved the whole thing !!
HAVEAGOODNIGHT !!
Brett
Jeez, did they !!
That’s Cool !! ... and I'm glad they liked them
Monday 10th May now
Yes, there is activity !!
There is a Fourty Seconds Video HERE
The start shows Ethan and a worker doing the Cladding on the Storage Sheds
They are at the back and not much has been done at the moment ... 8.15am
Bet the Cladding is finished today !!
The end of the video shows a guy roller painting the Eaves
There is also a photo below of a guy building the door frames for the Sheds
Will go back around lunch time or so
PS - Seven Cars Are On Site !!
Brett
Good to hear !! ... and Thanks
Geoff
10.45am now and there is 'RAIN' at Trinity
Only Light now but Steady and getting Harder
Might not stop the work - BUT - it will stop me walking !!
Will wait and see what happens
Geoff
Fortunately the rain stopped at midday
And it is 1.20pm Monday now
Three Photos are below
Brett, as you saw, the back of the Storage Sheds is almost finished
And there are Two Doors hanging and swinging !!
Dear Sharon aka Wife ... I Was Right !!
The Green Doors In Unit Four Were For The Storage Sheds !!
Painting "bits and pieces" still going on in each of the Units
Hope to get back there tonight ... Your Mum has a 4.00pm knock-off ... we shall see !!
Brett
Okay ... Great ... and Thanks
And it's 5.15pm Monday in Cairns now !!
Three Photos below
STORAGE SHEDS
#01 = the end near the street is finished
#02 = not quite finished
#03 = all four doors are where they should be !!
Brett
Looking Great !!
Tuesday 11th May at 8.35am
Two Photos below
FIRST
Cladding continues on the Storage Sheds
Finished the end and are now doing the front
Plus an electrician is there doing what he's got to do !!
SECOND
Sharon's New Kitchen
Maybe she could cook there tonight ??
PS -- Ten Cars Are Parked On The Street !!
Brett
Nice One !!
I'll message later when I can make it
It's now 11.30am on Tuesday
And below are Two Photos
The Cladding ?? ... Almost Finished !!
It is Tuesday the 11th now at 6.35pm
There Are Two Photos below
The Storage Shed Cladding is finished !!
These shots were taken from Trinity Beach Road !!
And as I left our street, turned right at the corner !!
And walked to the Baseball / Workout !!
Left here at 3.40pm ... got there at 4.15pm !!
Just to see if I could do it ... and I did !!
Brett
Good effort !!
And the Two Pics look great !!
Wednesday 12th May 2021
Thursday 13th May 2021
Friday 14th May 2021
Saturday 15th May 2021
"Carport Ceilings"
"Storage Sheds"
"Rendering the Block Side Fence"
Note from Geoff to Brett
8.45am and I'm back from "The Walk"
There is One Video HERE - Twenty Three Seconds
It shows that the Ceilings are now going into the Carports
The First Photo is another shot of the front of the Storage Sheds
They look terrific, eh !!
The Next Two Photos show that Ash is finally doing some work !!
Tidying Up and Rubbish Removal
HAVEAGOODDAY !!
Brett
Thanks !!
And it is around 2.15pm on Wednesday
There are Two Videos attached
Number 01 - Fifty Seconds
The Carport Ceilings on the left side are Finished !!
Number 02 - Fifty Seven Seconds
Starting the right side now
There are also a couple of Painters around
With sandpaper in their hands and working on the door frames
Brett
Good Stuff !!
Geoff
Every Day Now ... Something Happens !!
Sharon to Brett at 5.50pm Wednesday
And not good light for photos
The right side carport ceiling almost finished
Dad will send photos tomorrow morning when it is all done
Brett
No worries
Thursday morning now at 9.30am
There are Three Photos below
And yes, the Ceilings on the right side are finished !!
Ethan was just doing a final little bit of grouting
Then the Shed Doors were opened and they started lining the insides
There are also Painters inside Unit Four ... another coat of paint
I did not go in as I don't want to swallow a bucket full of paint fumes !!
Brett
They look big !!
Geoff
SHEDS ==== THEY - ARE - BIG !!
.
Thursday at 2.20pm and I just got back
NOTE ... there are "NO" photos or videos !!
Firstly, there were guys working in each of the Four Sheds
I didn't want to stick my camera in their faces and be "a big pain in the arse"
Secondly, paint fumes are still flying about
Will wait and see what the story is tomorrow
PS ... yes, I wore a Hat !!
.
Friday 14th at 9.45am and I am back from "You Know Where"
There are Two Videos attached
Number 01 - - Thirty One Seconds
The guys are starting to "Render The Block Side Fence"
As you can see, at the moment they are Grinding off all the 'garbage'
The boss reckons it will take two / three days to finish the job
Number 02 - Twenty One Seconds
Ethan and mates are finishing off the internal walls and ceilings
This is a "fun" video of one of the Storage Sheds !!
Really a bit too small for photos or videos !!
Just as a matter of interest ... Storage Shed Sizes:-
HERE = 107cm wide x 101cm deep
NUMBER THIRTY TWO = 230cm wide x 88cm deep
We have two sets of Steel Shelving which will fit perfectly depth wise !!
Very Happy Parents !!
Had a look in a couple of the Units
The Painting goes on but, really, there are no visible changes to photo / video
Brett
Progress !!
At least I didn’t get a headache from that video !!
Will the bike fit in there also ??
Geoff
The next video ??
I will spin and spin and spin again !!
Coudrey's Bike = Yes, It Will !!
Geoff
And the "Rendering" is going to be "The Next Big Change", eh !!
Geoff at 12.00pm
The Grinding along the Block Side Fence is all finished
And there is One Photo below
Saturday at 7.30am and I just did a 'drive-by'
Ethan and one other car
Could be "MORE ACTION" today !!
We were at "#32" at 1.30pm
Can't see any changes at all
Maybe it was inside work - etc etc - if anything ??