The Swimming Pool

The Pool Pump / Shed ... Page #01

ten photos

Preparing and Concreting the Slab

Thursday 27th October 2011

The area has been marked out ... water pipes and electrical conduit

The boxing has been made up ...

... and it's now being fitted in place

Ready for the concrete ...

... which is now being done

Almost ...

!! Finished !!

****************************************************************************

Friday 28th October 2011

The boxing has now been removed

NOTE - the white capped pipe on the left is an existing sewerage inspection point

****************************************************************************

Wednesday 16th November 2011

A post was concreted into the ground ... by Geoff ...

... a cross beam was attached and the switches and outlets have been installed and connected